New Service Installation Requirements
Please complete our online Commercial Service Application 6 weeks prior to the excavation of your foundation. Before services and meters can be installed, the following conditions must be met:
- Final building site plan must be e-mailed to gisland@uppco.com (electronic version in Microstation or Autocad format) or mailed to UPPCO at: Upper Peninsula Power Company, GIS Services, P.O. Box 19001, Green Bay, WI 54307 (paper version).
- Smaller jobs without an architectural building site plan can e-mail a Property Site Sketch & Liability Waiver form to businesscenter@uppco.com or fax to 800-305-9754.
- Electric Load Data Form must be completed within 3 business days of submitting your application.
- The construction site and building foundation must be back-filled to within 6" of final grade.
- The service route is to be cleared 10' wide of brush, building materials, etc.
- The electric metering equipment installed.
- If a cement pad for the transformer was poured, the pad must be cured for 10 days.
- An electrical inspection is required.
- Any private underground facilities must be marked and paths located.
- Permits and easements need to be signed and on file with UPPCO, when determined necessary by the utility.
- All service construction charges must be paid in advance of construction.