|
|
Home >
Electric Rates >
Customer-Owned (Parallel) Generation
Customers have the option to install their own on-site electricity generating systems,
such as wind turbines, solar photovoltaic systems or biogas systems, and connect them to
the Upper Peninsula Power Company distribution system. This process is called
"interconnection."
UPPCO is committed to making the interconnection process as easy for our customers as
possible. At the same time, the process must be conducted in a manner that is safe and
cost-effective for UPPCO and our customers.
The following information will guide you through the steps and requirements necessary
to interconnect a parallel system to the UPPCO electric distribution system.
For Systems 30kW or Less
- Start the Interconnection Process
Contact Kevin Pitts to review your project:
Phone: 920-433-4964
E-mail: klpitts@wisconsinpublicservice.com
- Review and Understand the Rates and Requirements
- Complete Interconnection Application
Complete and submit the Michigan Generator Interconnection Application, with the applicable review fee, to:
Attn: Kevin Pitts
Upper Peninsula Power Company
P.O. Box 19007
Green Bay, WI 54307-9007
- Application Review
Your application will be reviewed by UPPCO to determine if it contains all of the
information required to begin the interconnection process. You will then be notified
by UPPCO regarding the status of your application. If the application is incomplete,
additional information will be requested.
- Determine if Distribution Study is Needed
After your application is considered complete, UPPCO will determine if a distribution
study is needed. This study is to assess the level of impact your system will have
once connected to our grid.
If the study is required, you will be notified with the cost of that study. Upon
written authorization to proceed, and payment of the applicable fee, we will
complete the distribution study.
- Discuss Distribution Study and Review Interconnection Options & Costs
Once the study is complete, UPPCO will contact you to discuss all of the options
available — along with their associated costs — and the project timeline
for the interconnection of your parallel generation system.
- Installation of parallel generation and Distribution System Upgrades
You will need to install your generating equipment within a mutually agreed upon
timeframe. After receipt of payment for the agreed-upon interconnection costs, we
will perform all work needed to upgrade our distribution system to accommodate your
parallel generation system.
- System Testing
When the installation of your system is complete, UPPCO must be notified and given
the opportunity to witness or verify the system testing. This could include:
- Witnessing commissioning tests;
- Performing anti-islanding tests; or
- Verifying the protective equipment settings
- Interconnection Agreement
Before parallel operation can begin, a Generator Interconnection and Operating Agreement
will need to be completed and signed by the applicant and Upper Peninsula Power Company.
Back to Top
For Systems Greater than 30kW
- Start the Interconnection Process
Contact Bruce Hahn to review your project:
Phone: 920-433-1461
E-mail: bhhahn@wisconsinpublicservice.com
- Review Requirements and Complete Interconnection Application and Agreement
Based on the size of your parallel generation project, review the Michigan Generator
Interconnection Requirements. Then, complete the included Interconnection Application
and Interconnection and Operating Agreement.
Submit the completed Interconnection Application and Interconnection and Operating
Agreement, with the applicable review fee, to:
Attn: Bruce Hahn
Upper Peninsula Power Company
P.O. Box 19007
Green Bay, WI 54307-9007
- Application Review
Your application will be reviewed by UPPCO to determine if it contains all of the
information required to begin the interconnection process. You will then be notified
by UPPCO regarding the status of your application. If the application is incomplete,
additional information will be requested.
- Determine if Distribution Study is Needed
After your application is considered complete, UPPCO will determine if a distribution
study is needed. This study is to assess the level of impact your system will have once
connected to our grid.
If the study is required, you will be notified with the cost of that study. Upon
written authorization to proceed, and payment of the applicable fee, we will complete
the distribution study.
- Discuss Distribution Study and Review Interconnection Options & Costs
Once the study is complete, UPPCO will contact you to discuss all of the options
available — along with their associated costs — and the project timeline
for the interconnection of your parallel generation system.
- Installation of parallel generation and Distribution System Upgrades
You will need to install your generating equipment within a mutually agreed upon
timeframe. After receipt of payment for the agreed-upon interconnection costs, we
will perform all work needed to upgrade our distribution system to accommodate your
parallel generation system.
- System Testing
When the installation of your system is complete, UPPCO must be notified and given
the opportunity to witness or verify the system testing. This could include:
- Witnessing commissioning tests;
- Performing anti-islanding tests; or
- Verifying the protective equipment settings
Back to Top
Other Parallel Generation Resources
Back to Top
|