Is there a project timeline?

February 2020

MPSC issued order directing UPPCO to procure 125 MW of renewable generation.

May 2024

UPPCO purchased solar project development company and began value engineering.

November 2024

UPPCO secured 100% site control through lease & easement at the former Republic Mine site.

March 2025

UPPCO held a stakeholder information session in Republic Township seeking input and support.

April 2025

UPPCO files Solar Energy Facilities Exemption Certificate (Form 6052).

May 2025

UPPCO selects contractors for the project.

August 2025

Republic Township Board approves UPPCO's application for a Solar Energy Facilities Exemption Certificate.

September 2025

Primary road into the tailings area constructed and ~4,000 helical foundations installed, demonstrating start of construction.

May - June 2026

Site preparation (filling low areas on the tailings area) on-going and ~ 90% facility design completed.

August 2026

Anticipated start of solar panel installation.

2027

Targeted commercial operation.

*Timeline last updated 07/21/2026

How does the power from the Republic Solar project get distributed?
  1. All UPPCO customers will benefit from this renewable generation.
  2. The energy created from the Republic Solar project will be interconnected to the power grid at the Perch Lake Substation. Once the energy is interconnected at the transmission level it will be utilized by all UPPCO customers, whether near the Republic site or at any point on the UPPCO system.
Can residents expect elevated levels of sound disturbance?
  1. During construction: Yes. Residents can expect to experience elevated levels of sound during construction due to the transportation of construction equipment and crews. Varying sizes of trucks will be necessary for transportation of equipment to and from the construction site.
  2. During operation: Generally, no. Solar photovoltaics are a static method of power generation and produce very little noise during operation. Some low noise levels are expected in the vicinity around the power inverters and substation but nothing more than industry standard for such installations. Activity from operation and maintenance of the facility is anticipated to be minimal. UPPCO will be following the MI siting laws (PA233 of 2023) that include noise requirements for the project to be no louder than 55 dB. The existing Perch Lake Sub will be no louder than it is today after construction.
How is UPPCO planning to manage activities during the construction phase?
  1. Roads: Heavy-haul traffic will be routed through Republic Mine to bypass downtown Republic and will require DOT permitting. Also, contractors will be required to have a plan for managing traffic to/from site to ensure all County Rd permitting requirements are met and adhered to.
  2. Substation/Solar Array Design: Contractors and UPPCO engineers will evaluate the proposed substation and solar array design with a heightened emphasis on mitigating any potential negative visual aspects of the project.
  3. Generation – Transmission Line (G-T): The generation- transmission (G-T) line that will connect the solar project to Perch Lake Substation will be constructed underground and will not be visible.
Is solar power reliable in Republic Township?

Yes. Utility scale solar production estimates come from solar modeling software that utilizes regional data (weather/irradiance) combined with solar facility design characteristics (panel output/layout) to simulate the amount of solar energy that will reach the site over a given period.

Preliminary planning for the Republic site indicates winter months, defined as November through March, will contribute approximately 30% of the total annual production of a solar facility while the remaining non-winter months provide the remaining 70%.

How is UPPCO managing costs?
  1. Optimizing investment tax credits where appropriate to lower the cost of the project.
  2. Competitive procurement regarding proposals for development
  3. Competitive procurement of Engineering, Equipment, and Construction contracts
  4. Internal project management and engineering oversight of project deliverables.
Why is UPPCO investing in solar and renewables?
  1. Compliance with Michigan’s 2023 renewable & clean energy laws.
  2. With many of the tax credits, the costs of these projects are proving to be cost competitive when compared to other technologies
  3. As a portion of UPPCO’s power supply portfolio, renewable energy has an important place in the future sustainability of our electricity grid. Utility-scale solar will be part of this, so are the Company’s existing hydroelectric facilities.
What are some of the Project benefits?
  1. Specific Tax portion
    i. ~ $61,250 per year for 20 years to Republic Township
    ii. ~ $1,225,000 total
  2. Localized economic benefits from construction
    i. Utilization of regionally local, skilled-trade labor
    ii. Increase in general economic activity in localized region
    iii. Income multiplier effect – an increase in local incomes leads to an increase in local spending
  3. Revitalization of a former industrial site