How is UPPCO planning to manage activities during the construction phase?

  1. Roads: Heavy-haul traffic will be routed through Republic Mine to bypass downtown Republic and will require DOT permitting. Also, contractors will be required to have a plan for managing traffic to/from site to ensure all County Rd permitting requirements are met and adhered to.
  2. Substation/Solar Array Design: Contractors and UPPCO engineers will evaluate the proposed substation and solar array design with a heightened emphasis on mitigating any potential negative visual aspects of the project.
  3. Generation – Transmission Line (G-T): The generation- transmission (G-T) line that will connect the solar project to Perch Lake Substation will be constructed underground and will not be visible.