February 2020
MPSC issued order directing UPPCO to procure 125 MW of renewable generation.
May 2024
UPPCO purchased solar project development company and began value engineering.
November 2024
UPPCO secured 100% site control through lease & easement at the former Republic Mine site.
March 2025
UPPCO held a stakeholder information session in Republic Township seeking input and support.
April 2025
UPPCO files Solar Energy Facilities Exemption Certificate (Form 6052).
May 2025
UPPCO selects contractors for the project.
August 2025
Republic Township Board approves UPPCO's application for a Solar Energy Facilities Exemption Certificate.
September 2025
Primary road into the tailings area constructed and ~4,000 helical foundations installed, demonstrating start of construction.
May - June 2026
Site preparation (filling low areas on the tailings area) on-going and ~ 90% facility design completed.
August 2026
Anticipated start of solar panel installation.
2027
Targeted commercial operation.
*Timeline last updated 07/21/2026