Is there a project timeline?

February 2020

MPSC issued order directing UPPCO to procure 125 MW of renewable generation.

May 2024

UPPCO purchased solar project development company and began value engineering.

November 2024

UPPCO secured 100% site control through lease & easement at the former Republic Mine site.

March 2025

UPPCO held a stakeholder information session in Republic Township seeking input and support.

April 2025

UPPCO files Solar Energy Facilities Exemption Certificate (Form 6052).

May 2025

UPPCO selects contractors for the project.

August 2025

Republic Township Board approves UPPCO's application for a Solar Energy Facilities Exemption Certificate.

September 2025

Primary road into the tailings area constructed and ~4,000 helical foundations installed, demonstrating start of construction.

May - June 2026

Site preparation (filling low areas on the tailings area) on-going and ~ 90% facility design completed.

August 2026

Anticipated start of solar panel installation.

2027

Targeted commercial operation.

*Timeline last updated 07/21/2026